Grading Bond Release

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Checklist for Release of Grading Bonds

  1. Form PWE-106 completed
  2. Recorded Notice of Completion
  3. 35 working days have elapsed since NOC recordation.
  4. One set of the Soils Reports (original and final).
  5. Signed As-Built plans (mylars).
  6. Final Inspection (field items).
  7. City Landscape Architect notified of completion. A letter from the City Landscape Architect accepting landscaping is required if landscaping is part of grading permit requirements.
  8. Adequate funds in deposit account for staff time involved
    on the project(DE-####).

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Windows Media Player Download Windows Media Player Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer