At certain stages of the construction, you must schedule for an inspection. The following list represents the sequence of required inspections for a typical commercial/industrial building:
- Underground plumbing and electrical
- Foundation
- Tilt-up panels (if applicable)
- Pour strip (if applicable)
- Floor framing and deck pan (if applicable)
- Roof framing & roof nailing
- Exterior wall construction
- Interior wall framing and rough electric
- T-Bar ceiling and rough trades (electrical, plumbing & mechanical)
- Drywall nailing
- Lath nailing
- Electrical service
- Final Inspection
Schedule an Inspection
After all required inspections are approved and required approvals from other work groups are obtained, our Building Inspector will notify the utility company to release the electric meter and a Certificate of Occupancy will be issued. The issuance of a Certificate of Occupancy authorizes you to occupy and use the facility based on the permitted use shown on the Certificate of Occupancy.